Before any ground disturbance: Contact local 811, wait for all utility mark-out responses, and separately locate private underground lines.


Why Must the Test Hole Reach the Proposed Basin Bottom?

Subsurface infiltration rates govern dry-well and trench performance because water exits through the bottom and lower sidewalls of the excavation, not the turf layer. A shallow 6–12 in (15–30 cm) garden-level test misses restrictive clay pans, glacial till, or compacted fill that sit directly beneath the topsoil and cause basins to back up during sustained storms.

  • Match proposed invert and floor depth: After completing 811 and private utility locates, excavate the test hole to the exact elevation of the planned dry-well base or infiltration-trench floor, commonly 24–48 in (0.6–1.2 m) below grade for residential yard systems.
  • Keep the hole clear of footings and utilities: Contact local 811, wait for all utility responses, and separately locate private underground lines before any ground disturbance; maintain foundation, property-line, and septic setbacks, and never excavate near or below foundation footing elevation where soil removal can undermine structural support.
  • Verify what lies beneath the test floor: Even if a 36 in (0.9 m) hole drains well, an impermeable layer or seasonal high water table 6 in (15 cm) below the hole bottom eliminates vertical storage clearance.

What Pre-Dig Clearances and Site Checks Come First?

Every ground-disturbing test requires contacting local 811, waiting for all utility responses, and separately locating private underground lines before a shovel or auger touches the ground. Public 811 marks stop at utility meters or mains and do not locate private irrigation piping, landscape lighting, pool/spa lines, detached-garage power, or septic laterals.

Pre-Dig Check Required Action Physical / Legal Boundary
Public utilities Submit 811 locate ticket and wait for positive marks No digging inside tolerance zones without hand-exposing lines
Private buried lines Trace irrigation, low-voltage wire, propane, and private sewer/septic lines Separate from 811; owner-located or private-locate sweep
Legal overflow path Confirm surface or piped overflow route before approving infiltration Never route overflow to municipal sanitary sewers, floor drains tied to sanitary lines, septic systems, neighbor lots, or public walkways prone to icing
Setback & structural zone Measure distance from foundation walls, footings, wells, and septic fields Stay outside footing influence zone; do not undermine wall support
Safe excavation depth Measure planned test depth from finished grade Holes or trenches >= 4–5 ft (1.2–1.5 m) carry collapse risk and require shoring/sloping or mechanical testing from grade

What Test Hole Geometry and Tools Produce Reliable Data?

A uniform vertical-walled hole with a flat, uncompacted bottom and roughened sidewalls prevents artificial sealing and makes drawdown measurements repeatable.

Parameter Field Specification Purpose / Execution Note
Hole diameter / width 6–12 in (15–30 cm) round or 12 x 12 in (30 x 30 cm) square Large enough for a rigid measuring stick and clear visibility; small enough to pre-soak without excessive water
Bottom depth Equal to proposed dry-well or trench floor depth Typically 24–48 in (0.6–1.2 m) below grade; confirm dry, cohesive soil and never enter unshored cuts with sloughing walls or depth >= 4–5 ft (1.2–1.5 m)
Sidewall condition Lightly scarified (scratched) with a hand trowel or rake tooth Removes smooth clay smearing left by augers or post-hole diggers
Bottom protection 2 in (5 cm) layer of clean #57 washed angular gravel Prevents poured water from scouring mud into suspension and plugging floor pores
Reference datum Rigid straightedge laid across grade at the hole rim Fixed zero-point for all tape-measure or ruler readings

How Do You Execute Pre-Saturation and Timed Drawdown Logging?

Pre-saturating the surrounding soil before timing ensures you measure steady-state infiltration rather than initial dry-soil capillary suction. Dry soil pulls water rapidly into empty pores during the first fill, which can make a slow 0.2 in/hr (5 mm/hr) clay look like a passing 1.5 in/hr (38 mm/hr) sand until the surrounding ground swells and saturates.

Step 1: Pre-Soak the Test Hole

  1. Place bottom gravel and reference bar: Add 2 in (5 cm) of washed #57 stone to the flat floor and lay a straightedge across the top of the hole as your fixed measurement datum.
  2. Fill with clean water: Slowly pour water down the side or onto a splash baffle to 12–18 in (30–45 cm) above the gravel floor without washing soil off the walls.
  3. Maintain saturation: Keep water in the hole for at least 4 hours (or overnight in tight clay/silt soils) by refilling as needed so the wetting front stabilizes around the test zone.

Step 2: Run Consecutive Timed Drawdown Cycles

  1. Refill to test starting head: After pre-soaking, refill the hole to a clean starting depth (for example, 12 in / 30 cm above the gravel top) and record the exact distance from the straightedge datum to the water surface (D_start in inches) and the start time.
  2. Log water-level drop at fixed intervals: Measure the new distance from the datum to the water surface (D_end in inches) every 15–30 minutes for fast-draining soils or every 60 minutes for slower soils.
  3. Compute the interval rate (plain-text formula):
    • drop_in = D_end - D_start
    • infiltration_rate_in_hr = (drop_in / elapsed_minutes) * 60
  4. Repeat until consecutive readings stabilize: Refill and run at least 3 consecutive cycles (or until two consecutive readings are within 10% of each other). Use the final stabilized rate—never the first fast reading or an average skewed by the initial dry fill.
Reading Cycle Start Depth from Datum (in) End Depth from Datum (in) Drop (in) Elapsed Time (min) Calculated Rate (in/hr) Use for Sizing?
Pre-soak fill — — — 240+ — No (saturation only)
Cycle 1 18.0 19.2 1.2 60 1.20 No (still stabilizing)
Cycle 2 18.0 18.7 0.7 60 0.70 Check against Cycle 3
Cycle 3 18.0 18.6 0.6 60 0.60 (15.2 mm/hr) Yes (stabilized)

When Do Drought, Clay, or Subsurface Conditions Invalidate a Test?

Testing during extended drought, in smeared clay, or above an unverified seasonal water table produces artificially optimistic rates that fail during wet-season storms.

  • Drought and desiccated clay: Prolonged dry weather shrinks clay soils and opens temporary cracks that act like bypass pipes. A single 4-hour pre-soak may not swell desiccated clay back to its wet-season state; overnight saturation (12–24 hours) and multiple refill cycles are required before logging rates.
  • Auger sidewall smearing: Power augers and post-hole diggers burnish moist clay into a slick, low-permeability skin. Failing to scarify the walls and floor yields an artificially low reading, while testing only in unscarified fractured fill yields an artificially high one.
  • Perched or seasonal high water tables: A test run in late summer may show 1.0 in/hr (25 mm/hr) drainage at 36 in (0.9 m), yet fail completely in spring when groundwater rises into the basin floor. Check for gray mottling (redox features) or standing seepage in deeper probe holes.
  • Refusal on bedrock or hardpan: If excavation hits rock or cemented hardpan at or just below the planned basin floor, infiltration cannot safely be assumed without verifying clearance below the base.

How Do You Hand Off Raw Field Data to /calculators/?

Record the stabilized drawdown rate in in/hr, test-bottom depth, and subsurface observations, then pass those raw inputs to /calculators/ to evaluate storage volume, overflow risk, and pass/fail feasibility. For broader pre-hire assessment criteria and contractor scope definitions, see Site Assessment & Testing.

Raw Field Output What to Record How /calculators/ & Design Use It
Stabilized perc rate Final steady in/hr (and mm/hr) < 0.5 in/hr (< 12.7 mm/hr) flags high overflow risk; >= 0.5 in/hr (>= 12.7 mm/hr) proceeds to volume and clearance checks
Test-bottom elevation Depth in ft and in below grade Confirms test matches actual proposed dry-well or trench invert
Subsurface clearance Depth to water seepage, mottling, or bedrock Verifies vertical separation below proposed basin bottom
Contributing roof/yard area Horizontal projected catchment area (sq ft) Sizes storm inflow (Q_gpm and total storm gallons, e.g., 1,000 sq ft at 1 in/hr, C = 1.0 = 10.39 GPM / 623 gal per 1-in storm)
Legal overflow status Confirmed surface/piped discharge path Required even when perc rate is >= 0.5 in/hr

Common Field Execution Failure Modes

  • Testing in topsoil: Measuring percolation in the top 6–12 in (15–30 cm) of lawn soil produces false passing rates for a 36–48 in (0.9–1.2 m) deep basin.
  • Skipping pre-saturation: Logging the first water pour captures dry-soil suction rather than steady-state hydraulic conductivity.
  • Smeared clay walls: Leaving smooth auger-cut walls unscarified seals off natural soil pores and distorts drawdown.
  • No gravel floor buffer: Pouring water onto bare silt or clay suspends fine particles that settle and clog the hole bottom.
  • No legal overflow plan: Approving an infiltration basin solely on a >= 0.5 in/hr (>= 12.7 mm/hr) perc test without a legal overflow outlet causes yard flooding or foundation backup when storms exceed basin capacity.

DIY Scope vs. Pro / Structural Engineer Thresholds

Standard shallow perc testing (shallow in stable soil / 1.2 m deep, clear of utilities, footings, and septic systems) fits within DIY or pre-hire site assessment, whereas deep, wet, or structurally adjacent excavations cross into licensed contractor or structural engineer (PE) scope.

Physical Threshold Risk / Governing Condition Required Scope
Test hole or trench >= 4–5 ft (1.2–1.5 m) deep Trench or pit wall collapse hazard Pro excavation with shoring, benching, or remote-from-grade mechanical testing
Excavation near or below foundation footing elevation Undermining bearing soil and footing support Pro / geotechnical or structural oversight; do not hand-dig below footing plane
Unlocated private lines or permit/right-of-way crossing Utility strike or municipal code violation Licensed utility locator / permitted contractor
Multi-wall hydrostatic pressure or wet-basement seepage Subsurface water load exceeding simple yard dry-well scope Licensed waterproofing / drainage contractor
Wall bowing, leaning, step-cracking displacement, or active settlement Active structural distress Exits DIY and waterproofing scope; requires an on-site licensed structural engineer (PE)