Before any ground disturbance: Contact local 811, wait for all utility mark-out responses, and separately locate private underground lines.

What Pre-Hire Site Checks Determine Whether Infiltration Is Feasible?

Before contracting a dry well, require documented verification of design-depth percolation (>=0.5 in/hr / 12.7 mm/hr), clearance above seasonal high groundwater and bedrock, active 811 and private utility locates, code-compliant horizontal setbacks, and a legal surface overflow route (never discharging to sanitary sewers, septic systems, neighboring lots, or public walkways). If site conditions fail these acceptance thresholds, the contract scope must pivot away from subsurface infiltration before excavation begins. For field testing protocols and utility-clearance workflows, see Drainage Site Assessment & Pre-Construction Testing; for technical siting and disqualification criteria, see Seasonal High Groundwater and Shallow Bedrock Separation Requirements, Foundation, Property-Line, and Septic Setback Constraints for Dry Wells, and On-Site Infiltration and Temporary Storage for Flat Lots.

What Deliverables Belong in a Contracted Dry Well Scope?

A complete contracted dry well package must explicitly define setback verification, non-smeared excavation methods, washed aggregate and geotextile separation, upstream sediment pre-filtration, and a surface overflow route. Omitting any one of these items turns a subsurface storage system into a sealed underground mud pit.

Deliverable Contract Specification Acceptance Standard
Utility & Setback Verification Active 811 ticket, private-line locate, and measured horizontal offsets from footings, property lines, and septic components All public and private lines marked; setbacks documented before excavation
Non-Smeared Excavation Excavate from pit rim/side; no heavy equipment tracking on pit floor; hand-scarify any smeared clay/silt sidewalls or floor Native soil pores open and uncompacted at design-bottom elevation
Storage Assembly & Aggregate #57 washed angular stone (1.35–1.45 US short ton/yd^3 / 2,700–2,900 lb/yd^3), structural chamber or stone void, and non-woven geotextile Stone washed free of fines; usable porosity n (void/total volume) matches design calculation
Conveyance Piping Smooth-wall PVC (n ~ 0.011) or dual-wall smooth HDPE (n ~ 0.012); if single-wall corrugated HDPE is used, size at conservative n = 0.024 Continuous positive slope (>=1% or 0.12 in/ft; 2% or 0.24 in/ft preferred) with zero bellies
Sediment Pre-Filtration Upstream catch basin, sump trap, or leaf/debris screen installed ahead of the dry well inlet Accessible surface cleanout lid at grade; traps leaves, roof grit, and silt before storage entry
Surface Overflow Route Dedicated relief pipe or daylighted pop-up discharging to grade away from foundations Meets IRC 2024 R401.3 baseline (>=6 in / 152 mm fall in first 10 ft / 3.0 m, or 5%, for permeable ground; >=2% for impervious surfaces within 10 ft)

How Should Bids Compare Storage Volume, Stone Spec, and Runoff Sizing?

Bids should be compared on net usable storage volume (n), stone quality, pipe hydraulic capacity, and spoil haul-off assumptions rather than gross pit dimensions or total contractor tonnage. Two bids with identical pit dimensions can deliver very different effective storage if one uses unwashed gravel or miscalculates void space.

  • Catchment inflow baseline: Size the contributing roof or hardscape area using horizontal projected area:
    • Q_cfs = (C * i_in_hr * A_sqft) / 43,200
    • Q_gpm = Q_cfs * 448.831 (approx C * i * A / 96.25)
    • Anchor check: 1,000 sq ft (92.9 sq m) at 1 in/hr (25.4 mm/hr) with C = 1 produces 10.39 GPM (39.3 L/min) and 623 gal (2,358 L) per 1-in (25.4 mm) storm. Roof runoff coefficients C typically range from 0.90–0.95.
  • Net storage volume uses usable porosity (n): Dry-well storage capacity equals Pit_volume * n, where n is usable porosity (void/total volume), never geotechnical void ratio (e). For gravel-filled trenches or stone envelopes around pipe, compute Gravel_net_volume = stone_cross-section * length - pipe_OD_volume.
  • Stone purchase vs. spoil haul-off: #57 washed angular stone weighs 1.35–1.45 US short ton/yd^3 (2,700–2,900 lb/yd^3; verify local quarry weight). Soil bulking factors (1.2–1.3 for general soil, 1.3–1.4 for clay) apply strictly to excavated spoil haul-off volume—never to stone purchase quantities.
  • Full-pipe gravity capacity reference: Pipe sizing uses the Manning US equation Q_cfs = (1.486/n) * A * R^(2/3) * S^(1/2), where A is internal cross-sectional area (sq ft), D_id is internal diameter (ft), R = D_id / 4, and S is slope (ft/ft). Wall roughness n is ~0.011 for smooth PVC, ~0.012 for dual-wall smooth HDPE, and 0.016–0.024 for single-wall corrugated HDPE (use 0.024 for conservative sizing). Note that inlet grates, junctions, debris buildup, or submerged outlets can govern flow before pipe barrel capacity is reached.
Non-Price Bid Driver What to Verify Across Bids Why It Changes Scope & Longevity
Aggregate Spec #57 washed angular stone vs. unwashed gravel or crusher run Fines in unwashed stone migrate downward and seal the native infiltration floor
Spoil Haul-Off Allowance Explicit cubic-yard haul-off accounting for 1.2–1.3 (general) or 1.3–1.4 (clay) soil bulking Unaccounted spoil often gets re-spread over yard grades, altering foundation drainage
Pipe Wall & Alignment Smooth PVC / dual-wall HDPE vs. single-wall corrugated pipe Corrugated pipe holds sediment in ribs and requires steeper slope or larger diameter (n = 0.024)
Access & Surface Restoration Equipment access width, shoring for deep pits, and topsoil/turf restoration Tight side-yard access or deep pits (>=4–5 ft / 1.2–1.5 m) require smaller machines or trench protection
Cleanout & Overflow Access Accessible sediment trap lid and daylighted overflow termination Buried junctions without cleanouts cannot be maintained once roof grit accumulates

What Pre-Backfill Hidden-Work Inspections Are Required Before Closing the Pit?

Contractual hidden-work sign-off is required while the pit remains open to verify uncompacted, non-smeared pit floors, clean #57 washed aggregate and geotextile placement, continuous positive inlet pipe slope (>=1% or 0.12 in/ft; 2% or 0.24 in/ft preferred), upstream sediment trapping, and surface overflow continuity. For item-by-item pass/reject criteria, see the Dry Well & Infiltration Chamber Pre-Backfill Inspection. For general inspection documentation and concealment-release procedures, see the Pre-Backfill Drainage & Hidden-Work Inspection Checklists.

What Common Dry Well Failure Modes Should Warranty Terms Cover?

Workmanship warranties should explicitly cover installation defects that cause premature failure—including smear-compacted pit floors, fines-contaminated or unwashed aggregate, omitted upstream sediment traps, missing surface overflow outlets, pipe bellies or joint separation, and unverified groundwater intrusion. Contracts should tie warranty remedies to documented pre-backfill compliance with side-excavation, #57 washed stone, accessible cleanouts, and positive overflow grading. For detailed soil-related failure mechanisms and corrective measures in fine-grained soils, see Dry Well Design Limits and Adjustments in Clay and Silty Soils.

DIY Scope vs. Pro / Structural Engineer Thresholds

Dry well installation crosses from DIY-manageable yard work into licensed contractor or structural engineering territory based on excavation depth, proximity to foundation footings, and groundwater or structural symptoms.

  • DIY-feasible scope: Shallow infiltration pits or downspout catch-basin tie-ins shallow cuts in dry, cohesive soil, positioned well outside foundation footing influence zones, after 811 and private utility locates are complete, where design-depth percolation is >=0.5 in/hr (>=12.7 mm/hr) and a legal surface overflow route is established.
  • Licensed drainage contractor threshold: Any pit or trench reaching >=4–5 ft (>=1.2–1.5 m) deep (trench and pit-wall collapse hazard requiring shoring or benching), work crossing utility easements or requiring municipal permits, or multi-downspout systems needing machine grading to maintain >=5% (6 in in 10 ft) foundation fall.
  • Structural engineer (PE) stop-line: Any excavation near or below foundation footing elevation risks undermining structural bearing support and exits DIY and standard landscaping scope. Multi-wall hydrostatic pressure, wall bowing, leaning, step-cracking displacement, or active foundation settlement requires an on-site licensed structural engineer (PE) before any subsurface drainage work proceeds.