Before any ground disturbance: Contact local 811, wait for all utility mark-out responses, and separately locate private underground lines.
How Do Storm Inflow Volume and Effective Storage Determine Shortfall?
Storm-volume shortfall occurs whenever runoff entering the dry well exceeds the sum of open chamber volume and usable stone void volume, forcing excess water to back up or exit through a legal overflow outlet.
For a rapid cloudburst where infiltration during the storm is small relative to peak inflow, compare total storm inflow volume directly against effective dry-well storage:
- Peak runoff rate (rational method):
Q_cfs = (C * i_in_hr * A_sqft) / 43,200Q_gpm = Q_cfs * 448.831(approx.C * i_in_hr * A_sqft / 96.25) Anchor: 1,000 sq ft (92.9 sq m) at 1 in/hr (25.4 mm/hr) withC = 1.0produces 10.39 GPM (39.3 L/min) and 623 gal (2,358 L) per 1-in storm. Residential roofs typically useC = 0.90–0.95as a stated assumption. - Storm inflow volume:
V_inflow_gal = C * rainfall_in * A_sqft * 0.623V_inflow_cuft = V_inflow_gal / 7.481 - Effective dry-well storage volume:
V_stone_net = V_excavation - V_chamber_outerV_storage = V_chamber_inner + (V_stone_net * n)Usable porositynis void volume divided by total stone volume (do not substitute geotechnical void ratioe, which divides void volume by solid volume and overstates storage). - Zero-infiltration storm shortfall:
V_shortfall = max(0, V_inflow - V_storage)
Storm Inflow vs. Required Effective Storage Reference (Roof C = 0.95)
| Horizontal Roof Catchment Area | 1-in Storm Inflow (C = 0.95) | 2-in Storm Inflow (C = 0.95) | Peak Flow at 2 in/hr | Example Shortfall if Effective Storage = 500 gal (66.8 cu ft) on 2-in Storm |
|---|---|---|---|---|
| 500 sq ft (46.5 sq m) | 296 gal (39.6 cu ft) | 592 gal (79.1 cu ft) | 9.9 GPM (37.4 L/min) | 92 gal (12.3 cu ft) |
| 1,000 sq ft (92.9 sq m) | 592 gal (79.1 cu ft) | 1,184 gal (158.3 cu ft) | 19.7 GPM (74.7 L/min) | 684 gal (91.4 cu ft) |
| 1,500 sq ft (139.4 sq m) | 888 gal (118.7 cu ft) | 1,776 gal (237.4 cu ft) | 29.6 GPM (112.1 L/min) | 1,276 gal (170.6 cu ft) |
| 2,000 sq ft (185.8 sq m) | 1,184 gal (158.3 cu ft) | 2,367 gal (316.5 cu ft) | 39.5 GPM (149.4 L/min) | 1,867 gal (249.6 cu ft) |
How Do Wetted Bottom and Sidewall Area Assumptions Change Drain-Down Time?
Including sidewall area in the effective infiltration surface cuts calculated drain-down time by half to more than three-quarters compared to a bottom-only assumption, but overestimating sidewall permeability masks overflow risk if excavation smears clay or sediment clogs pit walls.
Compute estimated drain-down time from stored water volume, effective wetted area (A_eff), and design-depth infiltration rate (f_design):
- Drain-down time (cubic-foot basis):
T_drain_hr = V_stored_cuft / [A_eff_sqft * (f_design_in_hr / 12)] - Drain-down time (gallon basis):
T_drain_hr = V_stored_gal / (A_eff_sqft * f_design_in_hr * 0.623)
Choose the wetted-area assumption based on soil uniformity and wall condition:
- Bottom-only (
A_eff = A_bottom): Most conservative design baseline. Use when native soils are stratified, trench walls are smeared during digging, or fine sediment is expected to coat vertical faces. - Bottom plus partial sidewall (
A_eff = A_bottom + 0.5 * A_sidewall_full): Represents average wetted wall height as the water level drops from full to empty, assuming uncompacted, non-smeared sidewalls. - Bottom plus full sidewall (
A_eff = A_bottom + A_sidewall_full): Least conservative bound. Valid only for initial peak-head outflow when clean gravel meets uniform, permeable native soil with zero smearing.
Drain-Down Time Sensitivity (Example: 748 gal / 100 cu ft Stored in a 5 ft x 5 ft x 4 ft Wetted Footprint)
For a 5 ft x 5 ft (1.52 m x 1.52 m) footprint with a 4 ft (1.22 m) wetted depth, A_bottom = 25 sq ft (2.32 sq m) and A_sidewall_full = 80 sq ft (7.43 sq m).
Design Perc Rate (f_design) |
Bottom Only (25 sq ft) |
Bottom + 50% Sidewall (65 sq ft) |
Bottom + Full Sidewall (105 sq ft) |
Hydraulic Risk Flag |
|---|---|---|---|---|
<0.5 in/hr (e.g., 0.25 in/hr [6.4 mm/hr]) |
192.0 hr | 73.8 hr | 45.7 hr | High overflow risk; infiltration alone is unreliable |
0.5 in/hr (12.7 mm/hr) |
96.0 hr | 36.9 hr | 22.9 hr | Minimum threshold; requires overflow outlet and site clearances |
1.0 in/hr (25.4 mm/hr) |
48.0 hr | 18.5 hr | 11.4 hr | Moderate; verify bottom-only vs. sidewall sensitivity |
2.0 in/hr (50.8 mm/hr) |
24.0 hr | 9.2 hr | 5.7 hr | Rapid drain-down if water table and bedrock clearances hold |
What Material Volume and Site Testing Specifications Govern Dry Well Sizing?
This reference page isolates shortfall and drain-down time sensitivity; project-specific pit sizing, net #57 washed stone purchase volume, soil bulking for spoil haul-off, chamber displacement, and pre-excavation site testing inputs belong in the Dry Well Sizing and Infiltration Calculator.
What Step-by-Step Checks Verify Capacity Before Excavation?
Verify the hydraulic inputs behind the tables above before finalizing pit dimensions:
- Quantify catchment inflow: Measure horizontal projected catchment area (
A_sqft), apply the roof runoff coefficient (C = 0.90–0.95), and calculate design storm inflow (V_inflow_gal) and peak flow (Q_gpm). - Confirm net storage and shortfall: Compute
V_storage = V_chamber_inner + (V_stone_net * n)using usable porosityn(never void ratioe) and compare againstV_inflowto determine zero-infiltration shortfall. - Bracket drain-down sensitivity: Evaluate
T_drain_hrusing both bottom-onlyA_effand bottom-plus-partial-sidewallA_effat the design-depth percolation rate (f_design); if bottom-only drain-down exceeds the inter-storm window orf_design < 0.5 in/hr, upsize the footprint or route positive overflow.
For the complete pre-excavation siting and installation checklist—including 811 and private utility locates, groundwater and bedrock separation, foundation/septic setbacks, pretreatment, observation access, and legal overflow routing—see Dry Well Design and Specifications.
What Failure Modes Cause Premature Overflow or System Collapse?
Dry wells fail primarily when real-world infiltration area or void space drops below design assumptions, or when high groundwater and missing overflow paths trap water at the surface.
- Sidewall smearing during excavation: Scraping wet clay or silt along pit walls seals vertical pores, dropping actual
A_effto bottom-only capacity and doubling or quadrupling drain-down time. - Unfiltered sediment loading: Roof grit, mulch, and yard fines wash into the stone bed without a catch basin or debris screen, progressively filling void space (
n) and blinding the soil interface. - Confusing void ratio (
e) with porosity (n): Usingeinstead ofn = V_void / V_totaloverstates stone storage capacity and underestimates storm shortfall. - Submerged pit bottom from seasonal water table: High groundwater eliminates hydraulic gradient, reducing effective infiltration rate to near zero regardless of dry-season perc tests.
- Missing or submerged overflow outlet: Without a free-draining legal overflow at
>=1–2%slope (0.12–0.24 in/ft), surcharge backs up inlet pipes, floods downspout connections, and saturates foundation perimeter soils. - Inlet or grate bottlenecks: Undersized yard grates, debris-clogged inlets, or bellies in supply lines restrict inflow before dry-well storage is even utilized.
DIY Scope vs. Pro / Structural Engineer Thresholds
Shallow dry-well layouts in dry, cohesive soil that stay clear of foundation footings, septic setbacks, and energized electrical equipment fit homeowner planning once 811 and private utility locates are complete, whereas excavations >=4–5 ft (1.2–1.5 m) carry collapse risk and digging near or below footing elevation requires a pro. Active wall bowing, leaning, step-cracking displacement, or foundation settlement exits DIY and waterproofing scope entirely and requires an on-site licensed structural engineer (PE); full project-level DIY-vs-pro sizing thresholds are detailed in the Dry Well Sizing and Infiltration Calculator.