Before any ground disturbance: Contact local 811, wait for all utility mark-out responses, and separately locate private underground lines.
How Do Mode 1 and Mode 2 Work Together?
The calculator coordinates two independent tabs: Inflow & TDH System Curve (Mode 1) estimates sustained inflow from a timed basin rise and generates your plumbing's TDH system-curve checkpoints (0, 20, 35, 50 GPM) so you can compare them against a pump's published performance curve, and Backup Battery Runtime (Mode 2) converts usable battery watt-hours, battery-side power draw, standby draw, and duty cycle into estimated runtime hours while flagging inflow deficits.
Mode 1: Inflow & TDH System Curve Inputs and Outputs
| Calculator Input | Unit / Format | Engineering Role |
|---|---|---|
Basin Inside Diameter (D_basin) |
18 in, 24 in, or custom in |
Models a straight empty vertical-wall basin (1.10 gal/in at 18 in, 1.96 gal/in at 24 in) |
Measured Water Rise (Delta_h) |
in |
Vertical water rise measured during pump-off interval |
Pump-Off Interval (t_rise) |
min |
Elapsed time for Delta_h to compute sustained inflow (GPM) |
Static Vertical Lift (H_static) |
ft |
Vertical elevation from minimum sump water level to discharge high point |
Straight Discharge Pipe Length (L) |
ft |
Single-diameter straight pipe length (uses Sch 40 PVC Hazen-Williams C = 150) |
Discharge Pipe Inside Diameter (d_in) |
1.5-in (1.610 in) or 2-in (2.067 in) |
Actual Sch 40 PVC ID; sets both pipe friction and fitting equivalent length |
90° Elbows |
whole count | Adds 4.0 ft (1.5-in) or 5.2 ft (2-in) equivalent length per elbow inside friction only |
| Check Valve | One valve or None |
Adds 10.0 ft (1.5-in) or 13.0 ft (2-in) equivalent length inside friction only |
Peak Storm Design Margin (designMargin) |
1.0× (default), 1.25×, or 1.5× |
Multiplies measured inflow (GPM) to compute target design flow and target TDH checkpoint (for example, 18-in ID pit rising 6 in in 1 min = 6.61 GPM, and 1.5× margin = 9.92 GPM) |
Mode 1 Outputs: Basin capacity (gal/in), sustained inflow (GPM), optional target design flow (GPM when designMargin > 1), total fittings equivalent length (ft), TDH at measured inflow (ft) and at target design flow (ft), and a 4-point System Curve Checkpoints table (0, 20, 35, 50 GPM showing Friction and TDH) alongside the live TDH SVG curve showing both points. The widget does not plot a manufacturer pump curve—compare both TDH points against the pump's published curve so delivered GPM meets or exceeds your design flow.
Mode 2: Backup Battery Runtime Inputs and Outputs
| Calculator Input | Unit / Format | Engineering Role |
|---|---|---|
Battery Voltage (V) |
V (default 12 V) |
Multiplies rated Ah to establish nominal watt-hours |
Rated Battery Capacity (Ah) |
Ah (default 100 Ah) |
Nominal battery rating (enter the manufacturer's usable rating adjusted for expected ambient battery temperature) |
Battery Chemistry (DoD) |
AGM (50%) or LiFePO4 (85%) |
Sets usable depth of discharge (0.50 or 0.85) |
| Operating Pump Draw & Unit | Watts or DC Amps |
Battery-side input draw (for AC inverter systems, pre-divide AC pump watts by inverter efficiency P_batt = P_ac / eta_inv) |
Controller / Inverter Standby (P_standby) |
W (default 5 W) |
Continuous idle draw added to average power (P_avg = P_run * D + P_standby) |
Duty Cycle (D) |
% (0–100%) |
Fraction of each hour modeled for electrical runtime |
| Backup Pump Flow at Operating TDH | GPM |
Pump output read from pump curve at your Mode 1 operating TDH |
| Storm Inflow | GPM |
Sustained storm inflow entering the basin |
Mode 2 Outputs: Usable energy (Wh), Battery runtime at selected duty cycle (hr, e.g., 17.14 hr at 25% on 12V 100Ah 50% AGM drawing 120W + 5W standby), Minimum duty cycle to match inflow (%, or 'Exceeds 100% (pump undersized)' when inflow > pump flow), Average battery-side input (at keep-up duty) (W), and Runtime while keeping up with inflow (4.80 hr when 20 GPM inflow = 20 GPM pump forces 100% continuous 125 W draw, or 'Pump cannot keep up with sustained inflow' / 'No hold' in the diagram when inflow > pump flow). Note: Mode 2 uses the entered battery capacity directly and does not apply a temperature curve; for cold basements or garages, enter the battery maker's temperature-derated Ah rating.
How Do You Measure Basin Inflow and Static Lift?
The calculator computes empty vertical-wall basin inflow directly from Basin inside diameter, Measured water rise (in), and Pump-off interval (min). If a large pump housing or thick riser displaces a significant share of the measured band, subtract that submerged displacement (V_disp_gal) manually when verifying field inflow. Static lift (H_static) is strictly the vertical elevation difference between the minimum sump water level and the discharge outlet or vented gravity high point; horizontal runs do not add to H_static.
| Vertical-Wall Empty Basin ID | Volume per Inch (gal/in) |
Volume per Foot (gal/ft) |
Metric Equivalent (L per 25.4 mm) |
|---|---|---|---|
| 18 in (457 mm) | 1.10 gal/in |
13.20 gal/ft |
4.16 L |
| 24 in (610 mm) | 1.96 gal/in |
23.52 gal/ft |
7.42 L |
Custom ID (D_in) |
0.0034 * D_in^2 |
0.0408 * D_in^2 |
0.01287 * D_in^2 |
Plain-Text Inflow Formula (Widget & Manual Displacement Adjustment):
Widget empty-basin inflow:
Q_inflow_gpm = (pi * (D_in / 2)^2 * Delta_h_in / 231) / t_rise_min
Manual adjustment if pump/riser displacement V_disp_gal is significant:
Delta_V_gal = (V_per_in * Delta_h_in) - V_disp_gal
Q_inflow_gpm = Delta_V_gal / t_rise_min
For full field measurement procedures, delayed storm-inflow adjustments, dry-weather underestimation traps, and the 1.25–1.50x peak-storm sizing margin, see How to Measure Sump Pit Inflow Rate and Set a Peak Storm Margin.
How Is Total Dynamic Head (TDH) Calculated Without Double-Counting Fittings?
Total Dynamic Head is the sum of static lift plus flow-dependent pipe friction and minor fitting losses, and both friction and minor losses drop to exactly zero when flow (Q) is zero. The interactive calculator uses Option A — Equivalent Length (Sum(Le)) for single-diameter Sch 40 PVC (C = 150) inside the Hazen-Williams equation; if you perform a manual multi-segment or K-factor calculation outside the widget, choose either Le or K per fitting—never add Le directly to H_static, and never apply both Le and K to the same fitting.
Plain-Text System Curve Equations:
TDH(Q) = H_static + H_friction(Q) + H_minor(Q)
At Q = 0 GPM:
H_friction(0) = 0 ft, H_minor(0) = 0 ft => TDH(0) = H_static
- Option A — Equivalent Length Method (used by this calculator for Sch 40 PVC
C = 150):L_total = L_straight + Sum(Le) H_friction(Q) = 10.44 * L_total * (Q_gpm^1.852) / (C^1.852 * d_in^4.8704) H_minor(Q) = 0 - Option B — Manual Multi-Segment or Separate Minor-Loss Coefficient Method (
Sum(K)):v_i (ft/s) = 0.4085 * Q_gpm / (d_in,i^2) H_friction,i(Q) = 10.44 * L_straight,i * (Q_gpm^1.852) / (C^1.852 * d_in,i^4.8704) H_minor,i(Q) = Sum(K,i) * (v_i^2) / (2 * 32.174)
When pipe diameter changes along the discharge path (such as a 1.5 in vertical riser transitioning into a 2.0 in horizontal header), calculate H_friction,i(Q) separately for each segment manually using its own d_in,i and L_i, then sum all segments to build the system curve. For complete PVC roughness (C = 150) friction tables, fitting Le/K lookup values, diameter-effect comparisons, and system-curve intersection walkthroughs, see Sump Pump Total Dynamic Head (TDH) and System Curve Relationships.
When Does Backup Battery Runtime Fail to Equal Flood-Prevention Hours?
Backup battery runtime only estimates how long the battery can power the pump; if the pump's output at operating TDH (Q_pump) is less than sustained storm inflow (Q_inflow), water will continue rising in the basin and can overflow the floor even while the battery still has charge.
Plain-Text Battery Runtime Equations (matching Mode 2):
Usable_Wh = Voltage_V * Capacity_Ah * DoD_fraction
Battery-side run draw:
Native DC pump: P_run_W = P_pump_dc_W (or Voltage_V * Amps_dc)
AC inverter pump: P_run_W = P_pump_ac_W / eta_inverter (enter P_run_W as Operating pump draw)
Selected-duty power & runtime:
Selected_Duty = Duty_% / 100
P_selected_W = (P_run_W * Selected_Duty) + P_standby_W
Battery_Runtime_At_Selected_Duty_hr = Usable_Wh / P_selected_W
Keep-up duty & true storm holdover:
Required_Duty = min(1.0, Q_inflow / Q_pump)
Effective_Duty = 1.0 when Q_inflow > Q_pump; otherwise max(Selected_Duty, Required_Duty)
P_avg_W = (P_run_W * Effective_Duty) + P_standby_W
Runtime_While_Keeping_Up_hr = null when Q_inflow > Q_pump; otherwise Usable_Wh / P_avg_W
| Battery / Architecture Parameter | Typical Baseline Range | Engineering Impact |
|---|---|---|
Lead-Acid / AGM Depth of Discharge (DoD) |
0.50 (50%) |
Exceeding 50% accelerates sulfation and voltage sag under load |
LiFePO4 Depth of Discharge (DoD) |
0.80–0.85 (80%–85%) |
Maintains flatter voltage curve across usable capacity |
Native DC Pump Conversion (eta) |
1.00 (no inverter) |
Eliminates DC-to-AC conversion loss and inverter idle draw |
AC Inverter Efficiency (eta_inv) |
0.80–0.90 (80%–90%) |
Adds 10%–25% power penalty plus continuous no-load standby draw |
Worked Backup Check (12 V, 100 Ah, 50% AGM = 600 Wh, 120 W run, 5 W standby, 25% entered duty):
- Adequate (
20 GPMpump,5 GPMinflow): Required duty is25.0%(P_avg = 35 W); Battery runtime at selected duty cycle (25%) and Runtime while keeping up with inflow both read17.14 hr. - Matched / Duty Insufficient (
20 GPMpump,20 GPMinflow,25%entered duty): Battery runtime at selected duty cycle (25%) still reads17.14 hr, Minimum duty cycle to match inflow is100.0 %, average keep-up draw rises to125 W, and Runtime while keeping up with inflow drops to4.80 hr(continuous run with zero reserve). - Deficit (
20 GPMpump,30 GPMinflow): Water continues rising at10 GPM; Minimum duty cycle to match inflow prints'Exceeds 100% (pump undersized)', Runtime while keeping up with inflow prints'Pump cannot keep up with sustained inflow', and the diagram displays'No hold'.
What Sizing Prerequisites and Hydraulic Pitfalls Govern Output?
Before sizing or trenching a discharge route, establish a legal stormwater outlet: sump discharge must never enter municipal sanitary sewers, basement floor drains tied to sanitary lines, or residential septic systems, and must not discharge onto neighboring lots or ice public sidewalks. Call 811, wait for utility marks, and separately locate private underground lines before any exterior digging, and never step into standing water contacting energized electrical equipment.
Hydraulic & Capacity Failure Modes
| Failure Mode | Hydraulic / Physical Cause | Observable Symptom | Corrective Engineering Action |
|---|---|---|---|
| Undersized Discharge Pipe | High velocity (> 8–10 ft/s) spikes H_friction |
Pump falls far left on curve; low GPM |
Upsize segment from 1.5 in to 2.0 in ID PVC |
| Double-Counted Fittings | Applying both Le and K to the same elbow or valve |
Calculated TDH overestimated relative to true system head | Apply one fitting method only (Le in widget, or K separately) |
| Omitted Fittings / Restrictive Elbows | Leaving out valves/elbows or choking flow with sharp fittings | Calculated TDH underestimated; real pump GPM drops in service | Include actual fitting losses; use sweeping elbows and full-flow check valves |
| Inverter Standby Drain | AC inverter left idle for days during intermittent rain | Battery depleted before peak storm arrives | Account for P_standby_W or use a native DC backup system |
| Inflow Exceeds Pump Output | Q_inflow > Q_pump at true operating TDH |
Continuous pump run while basin water still rises | Reduce TDH, add parallel primary/backup pump capacity, or fix surface grading |
For basin short-cycling, float-switch setup, check-valve commissioning, and overall system architecture, see Sump Pumps, Pits & Backup Systems and Sump Pump Sizing, Flow Rate & Total Dynamic Head. For pressure-rated pipe selection, wall penetrations, freeze-relief air gaps, and pressure-to-gravity transitions, see Sump Pump Discharge Piping & Freeze Protection.
DIY Scope vs. Pro / Structural Engineer Thresholds
| Condition / Physical Threshold | Scope Classification | Required Boundary or Action |
|---|---|---|
| Shallow discharge work (in verified dry, stable soil) with legal outlet | DIY Scope | Call 811 + locate private lines; verify legal stormwater outlet; match TDH |
Exterior trench depth >= 4–5 ft (1.2–1.5 m) |
Pro Excavation Threshold | Trench collapse hazard; requires proper shoring, sloping, or trench-box protection |
| Digging near or below foundation footing elevation | Pro / Structural Threshold | Risks undermining footing bearing support; stop excavation immediately |
| Multi-wall hydrostatic pressure or chronic high-inflow flooding | Pro Drainage / Waterproofing Scope | Requires engineered perimeter relief, dual-pump redundancy, and exterior grading |
| Utility easement, curb core, or public right-of-way crossing | Permitted Pro / Municipal Scope | Requires municipal permit, inspection, and approved curb/storm-tie detail |
| Wall bowing, leaning, step-cracking displacement, or active settlement | Licensed Structural Engineer (PE) Stop-Line | Exits DIY and waterproofing scope; requires on-site licensed PE evaluation |
For contractor work packages, pre-backfill inspections, and acceptance testing, see Sump Pump Installation & Upgrade Scope of Work. For ongoing inspection intervals, timed drawdown logs, and planned component replacement thresholds, see Sump Pump Service Logs & Planned Component Replacement.